Rebar installation for the side support (abutment) and wing wall of the new section of the Casitas Pass Road Overcrossing. Grading for the new northbound Highway 101 on-ramp at Casitas Pass Road is in the background.
Source: SB Roads
Nighttime Freeway Closures
- Highway 101 will have the following closures between Linden and Bailard Avenues
- Monday through Thursday nights, September 10th – 13th
- The northbound and southbound Highway 101 fast laneswill be closed starting at 8:00 pm and will reopen by 5:00 am daily.
- One freeway lane will remain open in each direction during the lane closures.
- Monday through Thursday nights, September 10th – 13th
Linden Avenue Overcrossing
- Work continues on the side supports (abutments) for the new section of the overcrossing. Crews will pour concrete for the first side support in this stage of work.
- Southern California Edison will raise electrical lines near the southbound Highway 101 off-ramp at Linden Avenue
- On Sunday night, September 9th, the southbound Highway 101 off-ramp at Linden Avenue will be closed from 10:00 pm to 5:00 am. Drivers can use the off-ramps at Reynolds Avenue or Casitas Pass Road during the temporary closure.
Casitas Pass Road Overcrossing
- Crews will continue removing dirt from the new median piles, install rebar cages, and will pour concrete. Work will occur nightly. Please see lane closures listed above.
- Wood form work and rebar installation continues for the side supports (abutments) – see photo. Crews will pour concrete for the side support footing.
- New northbound Highway 101 on-ramp at Casitas Pass Road
- Grading and installation of roadway base will continue.
Highway 101
- Carpinteria Creek Bridges (northbound and southbound Highway 101)
- Northbound bridge
- Crews will finish installing post tension steel cable through the bridge internal supports (stems) and then remove wood form and temporary supports (falsework).
- Southbound bridge
- Concrete has been poured for the bridge surface (deck). Crews will begin installing post tension steel cable through the bridge internal supports (stems).
- Northbound bridge
- Northbound Highway 101 sound wall between Linden Avenue and Franklin Creek (Nipomo Drive)
- Sewer line relocation is finished.
- Southbound Highway 101 sound wall south of Franklin Creek
- Crews will remove vegetation in preparation for the upcoming sound wall.
- Drainage improvements continue along northbound Highway 101 under the Casitas Pass Overcrossing.
Via Real
- Frontier Communications will be running their cables in a couple weeks.
- Via Real will have one lane open between Casitas Pass and Vallecito Roads for the next few months.
Upcoming Work: fall/winter
- The Highway 101 southbound off-ramp at Casitas Pass Road will close for up to 1 month. Detour maps can be viewed at SBROADS.com.