Source: SB Roads
Timeframe: October 7 – 13, 2018
** Nighttime freeway lane closures throughout the week will allow for the installation of Continuously Reinforced Concrete Pavement for the new northbound on-ramp at Casitas Pass Road. Utility work continues on Via Real between Casitas Pass Road and Hales Lane. Please see details below.
Freeway & Ramp Closures
- Highway 101 will have the following closures between Linden and Bailard Avenues
- Monday and Tuesday nights, October 8th & 9th
- The northbound Highway 101 fast lane will be closed starting at 8:00 pm and both northbound lanes will close at 10:00 pm. The northbound fast lane will reopen by 5:00 am daily.
- During the northbound lane closures on Monday and Tuesday nights, a detour will be signed on Bailard, Carpinteria, and Santa Ynez Avenues (see map below).
- The southbound Highway 101 fast lane will be closed starting at 8:00 pm and will reopen by 7:00 am daily. One southbound lane will remain open.
- Wednesday and Thursday nights, October 10th & 11th
- The northbound and southbound Highway 101 fast lanes will be closed starting at 8:00 pm. The northbound fast lane will reopen by 5:00 am daily, and the southbound fast lane will reopen by 7:00 am daily.
- One freeway lane will remain open in each direction during the lane closures.
- Monday and Tuesday nights, October 8th & 9th
Linden Avenue Overcrossing
- Work continues on the side supports (abutments) for the remaining width of the new overcrossing.
- Near Linden Avenue and Ogan Road, the Gas Company is relocating a gas line to accommodate improved freeway drainage facilities.
Casitas Pass Road Overcrossing
- Crews will continue work on the new median piles. Work will occur nightly. Please see lane closures listed above.
- Wood form work, rebar installation, and concrete pours continue for the side supports (abutments) and wing walls.
- New northbound Highway 101 on-ramp at Casitas Pass Road
- Crews will install Continuously Reinforced Concrete Pavement on the new on-ramp. Continuously Reinforced Concrete Pavement is a quieter roadway surface due to the lack of horizontal seams across the lanes.
Highway 101
- Carpinteria Creek Bridges (northbound and southbound Highway 101)
- Northbound bridge
- Work continues on the final bridge finishes.
- Southbound bridge
- Crews will finish up work on back walls and the safety barrier.
- Northbound bridge
- Crews will continue to grade and improve Carpinteria Creek under the new Highway 101 bridges.
- Drainage improvements continue along northbound Highway 101 under the Casitas Pass Overcrossing.
Via Real
- Frontier Communications will be running new communications cable on Via Real and Vallecito Road. Via Real will be closed Monday through Friday from 8:30 am to 4:00 pm daily between Casitas Pass Road and Hales Lane. During this work, northbound Highway 101 can be accessed via detours on Casitas Pass Road, Carpinteria Avenue, and Linden Avenue.
Upcoming Work: fall/winter
- The Highway 101 southbound off-ramp at Casitas Pass Road will close for up to 1 month. Detour maps can be viewed at SBROADS.com.